成都市粮油储备物流中心建设项目(一期)二标段24米跨预应力拱板屋盖 施 工 方 案
编制单位:中冶建工有限公司
2010年01月
0
目 录
1、编制依据„„„„„„„„„„„„„„„„„„„„„„„„„„„„„„„„2 2、工程概况及工程量„„„„„„„„„„„„„„„„„„„„„„„„„„„„2 3、作业前的条件和施工准备„„„„„„„„„„„„„„„„„„„„„„„„„3 4、作业的程序和施工方法„„„„„„„„„„„„„„„„„„„„„„„„„„6 5、质量保证措施„„„„„„„„„„„„„„„„„„„„„„„„„„„„„„19 6、安全和文明保证措施„„„„„„„„„„„„„„„„„„„„„„„„„„„21 7、附件1~5„„„„„„„„„„„„„„„„„„„„„„„„„„„„„„„„23
1
1、编制依据
1.1设计图纸及变更、图纸会审纪录
1.1.1国家粮食储备局无锡科学院设计的散装平房仓24跨拱板屋架施工图纸; 1.1.2设计交底及图纸会审纪录。 1.2规程、规范
1.2.1《混凝土结构工程施工质量验收规范》(GB50204-2002) 1.2.2《混凝土强度检验评定标准》(GBJ107-87) 1.2.3《建筑结构工程施工工艺标准》(QCJJT-JS02-2004) 1.2.4《建筑工程施工质量验收规范汇编》(建标[2002]212号) 1.2.5 《冷轧带肋钢筋混凝土结构技术规程》(JGJ95-2003)
1.2.6《预应力拱板屋架空中预制施工工艺》(ZL9617701.2) 专利技术及多项大跨度预应力钢筋拱板屋架空中制作、安装的施工经验进行编制。 2、工程概况及工程量 2.1工程概况:
2.1.1成都市粮油储备(物流)中心建设项目二标段共5幢平房仓组成,地处成都市青白江区弥牟镇火星村,单幢仓长108M;宽24M,A3型平面尺寸分别为3廒间3×36×24,仓房为砖混排架结构。
2.1.2预应力钢筋砼拱板屋盖是集承重、防水、隔热、顶棚等多功能板架合一的屋架体系,它由上、下弦薄壳板、肋梁、内隔板及斜拉筋等组成。拱板跨度24m,单榀宽1.2m,下弦肋高200mm,肋宽100mm,板厚45mm;上弦肋高120mm、板厚45mm,上、下弦由隔板连接成整体,并且每块板下有四块埋件,代号为M-1与圈梁连接。拱板上弦为二次抛物线,曲线方程为:Y=4FX(L-X)/L2,其公式中:L-跨度,F-矢高,F=L/10。
2.1.3 拱板混凝土强度等级C35;隔板砼C35;混凝土保护层厚度:上弦板为15mm,上弦肋梁25mm;下弦板和下弦肋梁均为20mm。 2.2工程量: 序号 1 2 3 4 施工项目名称 钢筋(CRB800) 钢筋(CRB550) 钢筋(CRB550) 钢筋(CRB550) 规格 ΦR5 ΦR5 ΦR6 ΦR8 工程量 备注 2
5 6 7 8 9 10 钢筋(CRB550) 钢筋(HRB335) 钢筋(HRB235) 混凝土 预埋件 水泥珍珠岩块 ΦR10 Ф12 Ф14 C35 长×高×宽 M-1[90×180mm] 2.3工期 序号 1 2 3 施工项目 A3-1~2号仓拱板施工 A3-3号仓拱板施工 A3-4~5号仓拱板施工 施工计划 2010年03月1日~2010年05月05日 2010年03月07日~2010年05月06日 2010年03月01日~2010年05月05日 以上工期根据现场工作面移交情况交叉施工,拱板浇筑总工期控制在70天内。 3 作业前的条件和施工准备 3.1应具备的条件
3.1.1 顶圈梁以下结构施工完毕,室内地坪硬化完毕; 3.1.2 临时道路硬化施工完毕; 3.1.3 夜间施工有足够的照明;
3.1.4 施工及消防用水、用电、用气、通讯有保障,能够满足施工要求; 3.1.4 垂直运输机械安装到位。 3.2施工准备
3.2.1组织技术人员认真学习设计施工图,掌握施工图纸的全部内容,熟悉设计目的、设计意图、领会设计效果。
3.2.2对施工用的设备和机具进行全面的检修,该校准的校准,确保有效、安全。 3.2.3钢材、水泥应有出场合格证,并按规定取样进行复验,复验合格后方可使用。根据设计要求,进行混凝土的试配,确定混凝土配合比。
3.2.4钢筋焊接和预应力筋张拉属特殊工序,施工前必须由专业的人员进行操作和进行连续监控。
3.2.5在顶圈梁预埋张拉台座埋件和布置张拉线的有关设备和搭设满堂脚手架。 3.2.6制作拱板上弦底模等。 3.3 作业人员配置及职责 人员配置 人数 资格 职责 3
专项负责人 1 技术人员 1 安全员 1 质检员 1 试验人员 1 有组织协调能力,有现负责人员组织配备、分工协调工作。 场管理经验 1、全面负责该工程的技术工作负责一切要求熟悉基础施工图,技术资料的收集。 有土建结构施工经验,2、编制施工指作业导书; 熟悉施工技术及验收规3、深入现场指导施工及时发现和解决技范。 术问题; 4、制定施工方法、工艺; 1、在上级安全部门的领导下,全面负责安全管理工作; 有五年以上现场工作经2、执行公司安全管理标准,遵循安全管验,熟悉《电力建设安理规程,作好施工现场的管理工作 全工作规程》,责任心3、负责施工现场的安全检查,制止违章强,忠于职守,有安全员作业。 上岗证,持证上岗 4、做好安监违章记录,为安全评比提供直接、真实的依据; 1、负责施工全过程的质量监督、检查及有质检工作经验,熟悉质保资料的搜集与整理工作; 《建筑施工质量检验及2、有权对不能保证质量的方案提出异议,评定标准》。熟悉施工请求有关领导批准; 图,经过培训,有质检4、对不合格的工序有权责令其修改,并员上岗证,持证上岗。 禁止下道工序的施工,同时报告有关领导; 负责施工过程中全部试验项目的试验工有丰富经验 作。 负责操作搅拌机及日常维护保养工作 经过劳动局培训合格,负责现场照明及维护工作 持证上岗 负责焊接、制作预埋件、对拉杆、钢筋骨架等 负责混凝土抹面 负责模板修理、木模制作、支模、拆模工作 熟悉本工种,技术熟练 负责脚手架搭拆 负责钢筋制作与绑扎工作 负责拱板隔板,珍珠岩块等小构件制作。 负责拱板起运就位工作 机械操作工 4 电工 焊工 砼工 木工 架子工 钢筋工 2 6 30 20 20 30 小件制作工 10 拱板运输 10 3.4作业机具(配备、等级、精度) 3.4.1仪器、仪表 序号 1 名称 经纬仪 规格 J2 精度等级 2" 数量 1台 计量检验 合格 设备用途 轴线测量 4
2 3 4 5 钢卷尺 线坠 水准仪 测力仪 50米 0.75Kg AL322 SYC—18D 5mm / DS32 2盘 2个 1台 2台 合格 合格 合格 合格 测量放线 吊线、校正 标高测量 张拉力检测 注:以上仪器均计量检验合格,精度满足要求。 3.4.2施工机械、机具 序号 1 2 3 4 5 6 7 8 9 10 11 12 13 圆盘锯 平刨、压刨 钢筋调直机 切断机 弯钩机 强制式搅拌机 插入式振捣器、振捣棒 平板式振动器 电焊机 钢筋张拉机 滑轮式运输车 液压式千斤顶[20T] 手摇葫芦 名称 数量 1台 各1台 1台 2台 2台 1台 6套 2套 2台 3台 4台 6台 6台 设备用途 木模板加工、制作 木模板加工、制作 钢筋加工、制作 钢筋加工、制作 钢筋加工、制作 混凝土制作 混凝土振捣 混凝土振捣 钢材焊接及予埋安装 预应力钢筋张拉 拱板运输 拱板运输 拱板运输 3.4.3施工工具 序号 1 2 3 4 名称 扳手 钢筋钩 撬棍 焊把 数量 10把 20把 5把 5个 序号 5 6 7 8 名称 木抹子 铁抹子 钢筋断线钳 数量 4把 4把 2把 施工机械、机具进行检修,保证运转良好;做好易损、易坏件的备品工作。 3.5材料和设备
3.5.1根据施工图做出钢筋、水泥、砂、石、外加剂等材料的预算,并将材料购买齐全,经监理见证取样、复试合格后方可使用。
5
3.5.2施工前用的钢板、角钢、模板、脚手管、扣件、U型卡、方木等准备齐。 3.5.3将施工用的对拉螺栓、水泥砂浆垫块、预埋件提前加工制作好。 3.6安全器具
准备好安全围栏、安全帽、安全带、绝缘手套、绝缘鞋、防护镜等。
序号 1 2 3 4 5 6 安全器具名称 安全帽 安全带 安全警示牌 绝缘手套 绝缘鞋 防护镜 数量 100个 30条 5个 5副 5双 4个 规格 / / / / / / 4 作业程序的步骤、方法及内容 4.1施工方案选择
4.1.1钢筋砼拱板屋架为板架合一构件,杆件数量多、施工复杂、质量要求高、施工难度大。为快速、优质、安全低耗地完成施工任务、拟采用《大跨度预应力钢筋砼拱板屋架空中制作安装》工艺施工技术。
4.1.2采用空中预制施工工艺技术,只需在地面进行隔板预制,重点在高空利用工程一端原有圈梁进行加固改造,形成张拉台座,完成下弦板预应力筋的张拉,并安装预制隔板和完成上弦板的制作,一次性完成拱板屋架混凝土的浇筑,待拱板屋架整体砼达到设计强度的85%时,实施放张和首次起顶,将拱板放置在设计的专用滑轮车上,再慢慢用滑轮车和手动(电)葫芦水平将拱板均匀拉动放置到设计位置上;与地面预制吊装或满堂脚手架现浇的施工工艺比较,不需要大型预制及堆码场地,不需大型机械吊装,不需搭设满堂脚手架。是一种耗用少,成本低,安全可靠的施工技术。 4.2作业程序的步骤流程
本次工程共5幢仓,主要分成三部分施工:(1)隔板预制 (2)A3-1#~2#,A3-4#~5#仓拱板屋架施工;(3)A3-1#~3#仓拱板屋架施工; 4.2.1隔板预制
采用重叠生产法统一在A3-2#,4#仓提前15天预制。作业步骤:测量放线 → 张拉台座制作→ 钢筋安装→ 模板安装→ 浇筑砼→ 拆除模板→ 刷脱模剂→ 钢筋安装 → 模板安装 → 砼浇筑 → 拆除模板 → „„每个台座重叠生产10榀方法均同。 4.2.2拱板屋架施工工艺流程:
6
准备工作 → 测量放线 → 搭设张拉台座 → 铺设张拉下弦预应力筋 → 安装拱板隔板 → 支上下弦模板 →绑扎下弦板的非预应力筋、上弦板钢筋及安装预埋件 →浇端头砼、安装保温块 → 浇下上弦砼 → 拆除模板、剪预应力筋放张 → 焊斜拉钢筋 → 拱板运输安装 → 校正和最后固定。 4.3作业方法 4.3.1 施工准备
施工准备包括预埋圈梁张拉台座,预制台座脚手架搭投。 4.3.2测量放线
4.3.2.1拱板屋架根据设计施工图纸进行放大样,便于制作模板。
4.3.2.2拱板隔板根据场地进行放线制作预制台座。共设10个作业台座,每个台座每批生产10榀隔板。
4.3.3隔板制作和安装
4.3.3.1本工程隔板统一在A2-2#仓,4#仓提前完成[平面布置图详附件3],为保证混凝土的内实外光,采用角钢焊制成定型模板[如图],焊缝认真打磨光滑,并用小型平板振动器在混凝土面上均匀振捣。
4.3.3.2隔板安装时用30×30×50砼垫块(垫块强度C40)垫起,将隔板锚固钢筋与拱板钢筋网片绑扎。
4.3.4 拱板张拉台座搭设
4.3.4.1 在各个仓中部各搭设一个台座,宽14.4米,每批生产12榀,每台班生产10榀。 4.3.4.2现浇圈梁的加固及台座设计圈梁改造是为使其用作张拉墩而对其进行加固。台座的设计如下图所示。在浇筑顶圈梁时, 可将混凝土强度等级提高一个等级,一同埋设张拉台座所需构件,并且要求顶圈梁顶面平整,预埋位置准确。(见附图4:),张拉台座处外的天沟外
7
沿等拱板完成后进行浇筑,以保证有足够的操作平台。 4.3.5 台座脚手架搭拆
4.3.5.1本工程台座采用满堂扣件式钢管脚手架施工,脚手管为φ48×3.5的钢管。脚手架的搭设必须保证脚手架能够承载拱板所有施工荷载重量要求,脚手架框架单元尺寸为1350×1350×10,由立杆(8000mm)、横杆(4000mm、6000mm)及扣件组成的支撑体系,立杆纵横间距为1350mm,步距为10mm。(见附件5)
4.3.5.2脚手架搭设时,首先地坪需进行混凝土浇筑,将脚手架的基础位置清理干净,并在立杆底部加扫地杆用扣件扣牢, 扫地杆距离地面高度不大于20㎝。立杆的相邻接头、大横杆的相邻接头都应错开,并不在同一步距内,其接头距大横杆的距离不要大于步距的1/3,立杆和大横杆的节点处必须设置小横杆,在脚手架拆除之前,节点处的横杆不能拆除。 4.3.5.3大横杆放置在立杆内侧,立杆与大横杆用直角扣件扣紧,每个节点不能缺扣。同一排大横杆的水平偏差不能大于架子全长的1/300;小横杆应尽量靠近立杆位置,用直角扣件与立杆扣紧。上下各层小横杆应沿立杆左右两侧分别设置,以减少立杆的偏心受力。小横杆与大横杆要相互垂直,两头要伸出大横杆外10㎝以上,防止受力后滑脱。剪刀撑搭设时,将一根斜杆扣在立杆上,另一根斜杆扣在小横杆的伸出部分上。最下面的斜杆与立杆的连接点离地面不大于50㎝。剪刀撑的两端除用回转扣件与脚手架的立杆扣紧外,中间还要增加2~4个扣结点,与之相交的杆件扣紧。应满堂架四周与墙锚拉。
4.3.5.4 在顶部立杆与立杆之间中部设置1根中48×3.5钢管顶撑,然后用50×100木楞间隔100mm铺设,底模采用20厚复合模板(或竹胶板)。(详附件5) 4.3.5.5 拆除脚手架前的准备工作应符合下列规定: 4.3.5.5.1 应由单位工程负责人进行拆除安全技术交底; 4.3.5.5.2 应清除脚手架上杂物及地面障碍物。
4.3.5.5.3 拆除作业必须由上而下逐层进行,严禁上下同时作业;
4.3.5.5.4 连墙件必须随脚手架逐层拆除,严禁先将连墙件整层或数层拆除后再拆脚手架;分段拆除高差不应大于两步,如高差大于两步,应增设连墙件加固;
4.3.5.5.5 当脚手架拆至下部最后一根长立杆的高度(约6.5m)时,应先在适当位置搭设临时抛撑加固后,再拆除连墙件;
4.3.5.5.6.当脚手架采取分段。分立面拆除时,对不拆除的脚手架两端,应设置连墙件和横向斜撑加固。
4.3.5.6 卸料时应符合下列规定: a、各构配件严抛掷至地面;
8
b、 运至地面的构配件应及时检查、整修与保养,并按品种、规格随时码堆存放。 C、拆除前,对脚手架做一次全面检查,清除所有多余物件,并设立拆除警戒区,与拆除作业无关人员禁止入内。
d、拆除时先将脚手架上的顶丝松开,然后将木方和模板整块拆下,拆下的构件用麻绳吊下,低处人工递下,严禁抛掷。拆下的构件及时分类并码放整齐或送到指定地点存放。 4.3.5.7拱板张拉台座脚手架受力计算: 4.3.5.7.1 计算依据:
(1)《建筑施工扣件式钢管脚手架安全技术规范》(JGJ130-2001) (2)《建筑结构荷载规范》(GB50009-2001) (3)《建筑地基基础设计规范》(GB50007-2002) (4)《建筑施工模板安全技术规范》(JGJ162-2008)
(5)工程设计图纸:根据施工实际情况,按满堂脚手架(宽15m×长23.5m×高8m)作为计算对象,脚手架搭设高度按8m计算(取最大高度计算),不考虑风荷载。材料选用扣件式钢管脚手架,规格ø48×3.5mm,立杆纵距La=1.35m,横距Lb=1.35m,步距h=1.m。 4.3.5.7.2计算参数:
La=1.35m,横距Lb=1.35m,步距h=1.m;立杆截面积A=4mm2;立杆截面抵抗矩W=(5.08×10)mm;立杆回转半径i=15.8mm;钢材抗压强度设计值fc=205kN/mm;
预制拱板的荷载在模板及其支撑体系上传递途径的设计为:
上弦荷载 → 隔板 → 下弦底模 → 楞木 → 满堂架水平钢管 → 满堂架竖向钢管 → 下弦荷载 地面混凝土垫层
4.3.5.7.3 立杆稳定性计算
(1)根据规范第5.6.2.3条LO=h+2a;lO=1.+2×0.1=1.74m。λ=lo/i=1740/15.8=110.13。查得ψ=0.502(查规范附录C表C第56页) (2)计算N(单根钢管的轴向力)
1、脚手架自重=0.14KN/m×8×1.35×1.35=2.04KN 2、架上拱板及模板重:
a、下弦(0.1×0.2×2+(1.21-0.2)×0.04)×24.5KN/m3=1.97KN/m b、上弦(0.1×0.12×2+(1.21-0.2)×0.04)×24.5KN/m3=1.58KN/m C、隔板 0.12×0.06×1/2×0.99×4×24.5KN/ m3=1.02KN d.节点0.05×0.16×1/2×0.99×4×24.5 KN/ m3=0.39KN
9
3
2
2
小计:(1.97+1.58+1.02+0.39)=4.96 3、单根立管承载拱板混凝土重量
(1.97+1.58)/1.20×1.35×1.35+1.61+1.02+0.39=8.41 4、模板重
a、下弦:(0.04×0.2×2+0.04×0.16×2)×8KN/ m3=0.23KN/m 下弦底模为满铺2CM厚木板:0.02×1.12×8KN/ m3=0.18KN/m c、上弦:(0.04×0.12×2+0.04×0.08×2)×8KN/ m3=0.13KN/m 0.02×0.97×8KN/ m3=0.155KN
节点:(0.04×0.18×0.97×2+0.04×0.1×0.97×2)×8KN/ m3=0.17KN d、拱板的模板重: 0.23+0.18+0.13+0.155+0.17=0.865KN/m 小计:0.23+0.18+0.13+0.155+0.865=1.56
4、单根立管承载拱板模板的重量:0.865/1.20×1.35×1.35=1.31KN 5、台座楞木及木板重:(楞断面4CM×10CM间距100,楞木上木板厚度2CM) (0.04+0.02)×1.35×1.35×8KN/ m3=0.87KN 6、施工荷载
2.5×1.35×1.35=4.56KN
N=(2.04+8.41+1.31+0.87)×1.35+3.6×1.4=22.09KN
7、根据稳定性计算公式:N/ψA=22090/(0.502×4)=.98 (1)预应力拱板的混凝土重力、钢筋重力、模板重力及施工荷载通过下弦底板模板传递到木龙骨,再由4根间距400的水平钢管传到横杆上,横杆上每根水平钢管的重力和间距相等,横杆上荷载按均布荷载计算。 10 q=12.43KN/m400AB钢管抗弯强度计算简图 (2)拱板下弦底模上的荷载 由本方案立杆稳定性计算式中的拱板混凝土及拱板模板重(不含底模)为: (4.96+0.865)/1.2×1.35=6.55KN/m (3)底模及底模下木龙骨重: (0.02×1.35+0.04×1.35)×8=0.65KN/m (4)间距400的水平钢管重: (3.8×1.35×4)/1.35=15.2Kg/m=0.152KN/m (5)施工人员及设备荷载标准值 2.5×1.35=3.4KN/m q=(6.55+0.65+0.152)×1.35+3×1.4=14.12KN/m M=(1/8)×14.12×0.42=2.82×105N·mm (6)钢管的截面特性: W=5.08cm f=205KN/mm M/W≤f (2.82×105)/(5.08×103)=55.51N/mm2 4.3.5.7.6 钢管横杆挠度计算: (5/384)×(ql4/EI)≤1/150 式中: E----钢管的弹性模量 I----钢管的截面惯性矩 q----作用在钢管横杆上的均布荷载 l----钢管横杆的跨度 数据:l=40cm;E=2.06×105N/mm2;I=12.10cm4 (5/384)×((141.2×404)/2.06×107×12.10)=0.019<40/150=0.27 故钢管横杆的挠度满足要求 4.3.5.7.7 钢管横杆连接扣件抗滑移力计算: 根据JQJ130---2001(2002年版)扣件抗滑移力为R=8KN;由横杆抗弯强度计算中可知,横杆 11 3 2 上的荷载为q=14.12×1.35=19.06KN,分别由横杆两端的两个扣件和立杆连接的两个扣件共三个扣件承担19.06/3=6.35KN 取预制台座处1630长檐墙为计算单元,计算檐墙体内墙面与室内0米交线0—0的力矩。 天沟栏水缘子:1.630×0.08×0.04×25×1.24=0.161KN-M 天沟底板:1.630×0.71×0.08×25×0.845=1.96KN-M 顶圈梁:1.630×0.49×0.36×25×0.245=1.76KN-M 檐墙:1.630×0.49×7.×19×0.245=28.40KN-M M稳=0.161+1.96+1.76+28.40=32.30KN-M (2)倾覆力矩M倾 M1=12×10.9×8.13=1063.4KN-M M2=28×10.9×8.02=2447.7KN-M M倾=1063.4+2447.7=3511.1KN-M (3)水平撑杆抵抗力矩M抵 M抵=M倾-M稳=3511.1-32.30=3478.2KN-M (4)水平撑杆纵向抗弯计算: 预制台座水平撑杆节间间距是400mm,水平撑杆壁厚为3.5mm,按两端固定计算纵向受压: a、水平撑杆截面积F=498mmF(规范附录B表B) b、水平撑杆回转半径i=15.8mm(规范附录B表B) C.λ=lo/i=(1.155×400)/15.8=29.24 d.ψ=0.918(查表) e.水平撑杆轴力N: N=4×205×0.918=92.02KN。 (5)水平撑杆根数计算n n=M抵/7.94N=3478.2/(7.94×92.02)=4.76(根)(其中7.94为水平撑杆至地坪O米交线0-0的高度) (6)水平撑杆间距计算: S=1630/4.76=343mm取400mm 水平撑杆按间距400mm 12 (7)拱板下弦下面模板(台座平面模板)抗弯强度计算: 拱板的隔板为提前预制,在达到设计要求强度后与拱板模板组合安装。板上弦浇筑时的荷载由隔板传递到隔板下面的两垫块。垫块尺寸80×50×50,80为木龙骨间距方向。底模下的楞木按与拱板跨度成垂直方向安装其净距为100,即模板跨度为100。模板采用高强合成板(竹胶板),厚度20mm。 a、荷载计算: 上弦混凝土重:(0.1×0.12×2+(1.2-0.2)×0.04)×2/0.1×1/2×24.5KN/m3=15.68KN/m 隔板混凝土重:(0.97×2+1.91×2)×0.12×0.06/0.1×24.5×1/2=5.08KN/m 上弦模板:(0.04×0.12×2+0.04×0.08×2)×8KN/m×2/0.1×1/2=1.28KN/m 施工荷载标准值:1.2×2/0.1×2.5KN/m2×1/2=30.3KN/m 由于垫块下模板计算单元面积太小,下弦混凝土及模板重量忽略不计。并由于拱板为隔榀生产施工荷载小于标准值,本计算按标准值计算。 q=(15.68+5.1+1.3)×1.2+30.3=56.8KN/m b、模板抗弯强度计算 M=1/8ql2 M/W≤fm 式中: M----弯距设计值(N·mm) q----作用在模板上的均布荷载。 L----模板跨度(即龙骨间距) W----截面抵抗距=1/6bh2 Fm----模板的抗弯设计值(N/mm2),按《建筑施工手册》(第四版)下表取11N/mm2 M=1/8×56.8×1002=71.18×103N·mm W=1/6×bh2=1/6×100×202=6.70×103 N·mm M/W=(71.18×103)/6.7×103=10.6N/mm2 式中: q=作用在模板上的均布荷载(N·mm) E=模板的弹性模量(N·mm2),E=1×104N/mm2 I=1/12bh3=1/12×100×203=6.77×104 13 (0.677×56.8×1004)/100×104×6.67×104=0.06<100/250=0.4 模板的最大挠度符合要求 (9)底模下楞木抗弯强度计算: 楞木采用40×100白杉,间距200mm。楞木下为φ48钢管支撑间距为400mm,根据受力特点将楞木视为跨度为400mm的多等跨连续梁,下面钢管为梁支点,楞木上取荷载最大的边跨按简支梁计算。 a、荷载计算: a.1 预制拱板钢筋混凝土重: 下弦:(0.1×0.2×2+(1.2-0.2)×0.04)×24.5=1.97KN/m 上弦:(0.1×0.12×2+(1.2-0.2)×0.04)×24.5=1.58KN/m 隔板:0.12×0.06×(0.97×2+1.91×2)×24.5=1.02 节点:0.05×0.16×1/2×0.99×4×24.5=0.39KN 每米预制拱板钢筋混凝土重1.97+1.58+1.02+0.39=4.96KN a.2 预制拱板模板重: 下弦:(0.04×0.2×2+0.04×0.16×2)×8KN/m3=0.23KN/m 0.02×1.12×8KN/m3=0.18KN(下弦底模为满铺2CM厚木材) 上弦:(0.04×0.12×2+0.04×0.08×2)×8KN/m=0.13KN/m 0.02×0.97×8KN/m3=0.155KN 节点:(0.04×0.18×0.97×2+0.04×0.1×0.97×2)×8KN/m3=0.17KN 每米预制拱板的模板重0.23+0.13+0.155+0.17=0.865KN 拱板钢筋混凝土及模板在楞木上的线荷载为: (4.96+0.865)/1.2×0.2=0.97KN/m 施工荷载在楞木上形成的线荷载 2.5×0.2=0.5KN/m a.3 楞木的抗弯强度计算: q=1.86KN/m3 400AB楞木计算简图 在楞木上形成的线荷载q为 0.97×1.2+0.5×1.4=1.86KN/m 14 最大弯矩M=1/8×1.86×4002=37.2×103N·mm W=100×502×1/6=41.66×103 木材的抗弯设计强度为fm=13.0N/mm2 M/W=(37.2×103)/(41.66×103)=0.<13.0N/mm2 楞木的抗弯强度满足要求。 (10)楞木的挠度计算: 楞木的弹性模量E=9000N/mm2 I=1/12bh3=1/12×100×503=104cm4 0.677ql/100×EI=(0.677×1.8×10×23)/(100×9×10×104)=3.6×10<23/250=9.2×10 楞木挠度满足要求 4 4 3 -2 -2 4.3.6钢筋工程 4.3.6.1预应力拱板屋架钢筋分为三种,Φ-Ι级 Ф-Ⅱ级和ФR钢筋,ФR钢筋作为拱板的预应力筋。 4.3.6.2普通钢筋和预应力筋进入施工现场应分批号堆放整齐,并及时填写试验委托单,试验员按规定进行取样并送交试验部门进行拉伸和冷弯试验。试验合格后方可使用到工程上。 4.3.6.3普通钢筋表面应干净,无损伤、油渍、漆污和片状老锈等缺陷。 4.3.6.4拱板下弦预应力筋为CRB800级Ф5冷轧带肋钢筋, 预应力钢筋严禁接头,并且应严格按照国家现行施工规程张拉并控制好混凝土的保护层厚度。 4.3.6.5拱板隔板预应力筋为CRB550级ФR5冷轧带肋钢筋,其应力值150N/mm2。单根张拉力1.8KN。 4.3.6.6预应力筋下料及铺设 a、预应力成盘钢筋,采用等长下料,按“应力下料法”即将钢筋用一固定的力拉紧,在固定力拉紧状态下量出所需要的长度,然后放松,用剪丝钳切断,就能达到等长。 b.台面在铺放钢筋前,应涂隔离剂,隔离剂不宜沾污钢筋,以免影响钢筋与砼的粘结(可在底模上每隔2米,横向放置一根Ф18短钢筋)。如果预应力筋遭受污染,应加以清洗干净,在生产过程中,应防止雨雪等冲刷台面上的隔离剂。预应力筋采用人工铺设,电动卷扬张拉机张拉。 4.3.6.7预应力钢筋制安 4.3.6.7.1梳筋板(锚板) 梳筋板(锚板)]采用20厚带加强肋的钢板,根据屋架前后两端的截面尺寸和预应力筋间距,加工制成两种规格:1200×420mm,1180×420mm如图所示。 15 R 4.3.6.7.2张拉设备 张拉设备采用电动卷扬张拉机,装有测力仪表,测力计应预先标定、标有测力荷载。张拉时,将标尺零位线对准所需张拉力的刻度,开动电机,达到预定张拉力时,碰块触动行程开关,电源自动切断,实现张拉力自动控击。 4.3.6.7.3应力测定 钢筋张拉时预应力检测采用杭州新华无线电厂制造的SYC—18D智能型钢筋测力仪,对张拉钢筋施工过程的应力变化进行检测,作好张拉记录,以保证张拉质量。 4.3.6.7.4夹具:采用扁扣式夹具进场时,应有出厂证明书。 4.3.6.7.5预应力筋张拉: a、采用单根对称张拉,张拉顺序为从中间到两边,从下到上,夹具锚固。张拉控制应力δcon=0.7fptk(10.99KN/根);张拉控制行程为65mm,锚具回缩值a≤5mm。 b、张拉机具与预应力筋应在一条直线上,同时每隔一段距离放一根相当于保护层厚度的圆钢筋头,以防预应力筋因自重而下垂,以及减小张拉时的应力损失。 c、张拉时应先拉靠近截面中心的钢筋,依次对称张拉,张拉完后应逐根进行应力补充,确保钢筋的张拉应力均匀、准确。张拉完后砼必须当天浇筑完毕,防止应力损失过大 4.3.6.7.6预应力钢筋张拉值校核: 预应力钢筋张拉时,伸长值应作伸长校核,钢筋张拉锚固后,应采用钢筋内力测定仪检查钢筋的预应力值,其偏差不得大于或等于设计规定相应阶段的预应力值的±5%。 4.3.6.7.7预应力筋放张: 设计要求混凝土强度达到85%及以上时预应力筋才能放松,根据施工经验一般浇筑完成3天即可。放张前,必须拆除侧模板,使构件自由压缩。在放松过程中,应先放松肋梁钢筋, 16 再放松板面钢筋,预应力筋应从两侧逐根交错放松。为了检查构件放松时钢筋与砼的粘结是否可靠,切断钢筋时应测定钢筋在砼内的回缩量。 4.3.6.7.8放张后及时焊接好斜拉筋,并从两端向跨中对称双面施焊,但不得同时两端同时焊接,焊接长度应≥120mm,高度≥6mm。 4.3.6.8非预应力钢筋制安 4.3.6.8.1工作程序为:确定用料→调直→切断→弯曲成型。 4.3.6.8.2 确定用料严格按翻样单上要求的规格、数量加工配制。 4.3.6.8.3对局部有弯曲的钢筋采用人工调直后,才能使用。调直用丝杠架子调直粗钢筋,对原材端头有弯曲及留下马蹄形毛边的用大锤调直,调直后应平直无局部曲折。 4.3.6.8.4钢筋在断料前,应将翻样单上同规格钢筋根据不同的长度,长短合理搭配,统筹排料。一般先断长料后断短料,减少短头、损耗。并避免短尺量长料,防止出现积累误差或错量。 4.3.6.8.5钢筋弯曲成型时,应根据翻样单上尺寸,先划出弯起点位置再弯曲。弧度筋制作时,其弧度严格按半径加工,应先根据该钢筋的半径在地面上实际放样,先加工一根钢筋,根据放样尺寸调整弯曲机的弯曲弧度,调整合适后再成批加工。 4.3.6.8.6钢筋在加工过程中如发现有脆断、劈裂等异常时,应及时向技术人员反映,并停止该批钢筋的使用,待重新试验合格确认后再使用。 4.3.6.8.7钢筋加工制作要听从现场施工负责人指挥,加工要根据现场需要加工,保证现场施工进度需要。钢筋加工的成品、半成品应有明确标识,码放整齐,并做好自检记录。 4.3.6.8.8钢筋接头:本工程非预应力钢筋采用绑扎接头 绑扎搭接接头的长度(La)为:(d为钢筋直径) HPB235钢筋 光圆钢筋 Ι 38d HRB335钢筋 带肋钢筋 II 40d 4.3.6.9钢筋绑扎: 4.3.6.9.1钢筋绑扎前,先用粉笔划好钢筋位置,然后再进行布筋、绑扎,保证绑扎整齐,要求横平竖直,规格、数量、位置、间距正确。并再次检查钢筋的规格、尺寸、数量,及使用部位是否与设计图纸相符,以确保准确。 4.3.6.9.2钢筋绑扎时,绑丝尾部要全部压向梁,板的内部,防止绑丝外露。在主筋上放好混凝土垫块,垫块采用水泥砂浆垫块。钢筋绑扎过程中及时调整钢筋间距及垂直度,实现钢筋工程的精品,为模板及混凝土工程创造良好的施工条件。 4.3.6.9.3钢筋绑扎过程中,如遇特殊情况或须钢筋代换时,必须征得监理和设计院工代同 17 意,并有工程洽商单材料代换单。 4.3.6.9.4绑扎钢筋时,注意预埋件位置,必须位置准确固定,不得碰撞移动。 4.3.7 预埋件安装 4.3.7.1预埋件加工要保证埋件的规格尺寸,钢板埋件表面要平滑,四边顺直,钢板的焊接变形要调平。 4.3.7.2埋件安装时先用卷尺在模板上量好尺寸,做好标示固定在钢筋上,严格按图纸要求的位置和标高安装。 4.3.7.3埋件安装要牢固可靠,保证在混凝土施工过程中不被碰动。 4.3.8模板工程 4.3.8.1根据拱板屋架的特点,为有利拱板模板安拆方便、加速周转,拟加工10套专用模板。 4.3.8.2模板的制作:制作前,先在平整地面上按1:1比例,用直角坐标法(横座500)放好大样,按样板制作上弦拱形底模及弧形边模。 4.3.8.3下弦板侧模的铺设:底模内侧模板采用40×150mm木模,外侧模板采用40×200mm木模,模板加固采用Φ14钢筋,两端制成U形,间距550mm的简易夹具进行内外侧模板的加固。 4.3.8.4上弦板模板铺设:上弦板底模板采用专用成品船型模板,与拱板隔板相互固定,侧模固定方法同下弦板侧模。 4.3.8.5模板的拆除:拆除时不能在成型好的拱板上敲打,拆上弦底模时,均应人工传递,严禁摔,扔,砸,敲,防止震裂拱板,做到轻拿轻放。 4.3.9 混凝土工程 4.3.9.1本工程混凝土确定采用现场机械拌合,混凝土供料方式由50型吊配合人力手推车进行。 4.3.9.2混凝土浇筑顺序为先两端,后跨中,先下弦,后上弦的浇筑顺序。混凝土浇筑完成时间不超过3.5小时,不得留设施工缝。如遇停电等特殊情况且该榀拱板浇筑完成70%以上可以采用人工振捣完成。 4.3.9.3混凝土的浇筑、振捣 4.3.9.3.1混凝土工程是结构成型的关键工序,作业过程中要严格控制和检查混凝土的坍落度及和易性,对坍落度超标的混凝土严禁使用。 4.3.9.3.2混凝土浇筑过程中,设专人监视模板、钢筋、脚手架等的情况,如发现变形、移动时,立即停止浇筑,采取有效处理措施,修复好后方可继续浇筑。 4.3.9.3.3混凝土施工以混凝土表面呈水平不再显著下沉和不出现气泡,表面泛出灰浆为准。 4.3.9.4混凝土养护:混凝土浇筑完成后采用塑料布覆盖养护, 如遇冬天须采用蒸气养护。 18 4.3.10 拱板高空就位 4.3.10.1就位顺序:起顶→放滑轮车→运输→临时固定→校正和最后固定。 4.3.10.2起顶:每榀拱板在台座圈梁上设置预留洞,放置QYL20T型液压千斤顶四台,每端两台。液压千斤顶起顶垫块为120×120×10钢板,当拱板砼强试达到设计强度的85%以上(一般为3天)时才能起顶。 4.3.10.3放滑轮车:液压千斤顶顶起一定高度后,放置专用滑轮车,落下千斤顶,滑轮车下用300×2500×10钢板每端两块,在拱板移动过程中,替换使用。 4.3.10.4运输:在山墙圈梁交横轴上分别埋设两根中18锚拉钢筋环,用于固定手动葫芦。拱板中心埋设中10的拉环,拉环距拱板边500,然后用手动葫芦沿横轴线拉动拱板,直到拱板就位位置。运输过程中要速度均匀,拉力均匀一致,到设计位置后,用千斤顶顶起拱板,取走滑轮车及钢板,落下拱板。 4.3.10.5运输拱板前应严格控制拱板中心线,用墨线弹于墙上,拱板预制中心线于控制中心线重合,然后临时固定。 4.3.10.6校正最后固定:拱板主要校正垂直偏差,检查时采用线锤或经纬仪,校正无误后,立即将拱板支座处预埋件与顶圈梁焊牢。 5 质量保证措施 5.1认真领会设计意图及施工特点,搞好技术交底,使参与拱板构件生产的人员严格按设计图纸及操作规格施工。 5.2混凝土工程施工质量保证措施。 5.2.1控制原材料尤其是水泥、混凝土外加剂的进货质量合格;砂石料严格控制含泥量及石粉含量,同一结构层的混凝土选用相同粒径的砂石料,严格控制水灰比及坍落度。 5.2.2考虑好模板之间的关系,计算好配模几何尺寸。 5.2.3为保证混凝土表面颜色一致,对混凝土配合比进行优化,混凝土搅拌时严格计量及校验;并保证混凝土连续施工。浇筑前,将杂物清除干净。 5.2.4用温水搅拌混凝土,以保证混凝土的入模温度,掺相应的缓凝型外加剂,保证混凝土入模时通风,加速模内混凝土热量散发。 5.2.5选择良好极配的骨料,严格控制含泥量,加强振捣,提高混凝土密实度和抗拉强度,减小收缩变形。 5.2.6控制混凝土坍落度和浇筑的连续性,保证强度要求。梁顶及板表面用木抹子抹平,同时用铁抹子压光,平整度达到规范要求;的预埋件位置必须准确。 5.2.7混凝土浇筑完开始养护,为保证混凝土表面质量,同条件试块强度达到规范要求时, 19 进行模板拆除,同时加强成品保护。 5.2钢筋工程施工质量保证措施 5.2.1钢筋原材料进行抽样送检制,资料及复试合格后方可使用。钢筋现场绑扎,进行划线确定位置,过程控制,确保符合设计要求,配筋准确合理,绑扎牢固、美观; 5.2.2钢筋焊接接头施工时,所有操作工均持证上岗; 5.2.3钢筋张拉时作好张拉记录。 6 安全和文明保证措施 6.1所有参加作业人员作业前参加技术及安全交底,掌握施工现场情况,了解每天的工作内容及安全、质量要求,听从管理人员指挥,不蛮干,做到“三不伤害”,安全文明施工。同时认真做好交制度。 6.2特殊工种操作人员如电焊工等应持证上岗,施工用电找电工,施工机具应按规定安装触电保护器,一机一台,并且要有良好的接零,所有的电源闸箱均应有防雨措施。 6.3 台座两端区域设置1.2米钢管护栏和安全网。钢筋张拉时两端不得站人;起运拱板时,板下严禁站人。 6.4当风速超过五级时,禁止起运拱板。 6.5施工场地平整坚实道路畅通,并实现水电通、道路通畅。 6.6夜间施工必须照明充足。 6.7安全防护设施齐全、完备。 6.8在施工过程中,项目部专职安全员负责监督检查本工程施工场所的安全施工、文明施工情况。对查出的事故隐患应立即督促整改。有权制止违章作业和违章指挥,有权对违章者进行经济处罚。参加安全交底,并到现场检查是否具备安全施工条件,监督安全措施的执行。 6.9施工人员的个人防护用品、用具齐全合格,并会正确使用和佩戴。 6.10在高处临边作业超过2m时,施工人员必须系好安全带和戴好工具袋、穿好防滑鞋,安全带应系在上方牢固的结构上,工具使用后应放入工具袋内,以免坠物伤人。 6.11 电动工具如角磨砂轮、 切割机等,操作时应戴绝缘手套、穿绝缘鞋。 = 6.12电、火焊应由专业人员操作,同时戴好防护眼镜和手套,穿劳保服。 6.13氧、乙炔瓶分开放置,间距为5m以上。 6.14患有恐高症的作业人员不得进行高处作业。 6.15 施工人员严禁酒后进入施工现场施工和现场打逗,应听从指挥,严格执行现场安全施工管理规定。 20 6.16杜绝野蛮施工,作到“三不伤害”,即不伤害自己、不伤害他人、不被他人伤害。 6.17认真检查预应力筋是否有缺陷,经常检查机具、台座、夹具有无松动或失效,防止张拉过程中发生断筋或钢筋滑脱伤人。 6.18张拉机具使用时,每天张拉前后,应对所用机具进行检查或维护。 6.19每天作业完毕后,必须清理干净现场,材料统一码放整齐,现场文明施工应做到“工完、料尽、场地清”。 附件1:总平面布置图 附件2:施工进度计划横道图 附件3:拱板隔板预制图、详图 附件4:拱板张拉台座预埋图 附件5:台座脚手架搭设图 21 附件1:总平面布置图 22 附件二: 施工进度计划表 23 附件3:隔板平面布置 24 附件4:拱板张拉台座预埋图 25 附件5:台座脚手架搭设图 26 因篇幅问题不能全部显示,请点此查看更多更全内容